Important works, financed entirely by the State for the benefit of the cathedral complex of Saint-Dié-des-Vosges, are being completed. On the cathedral, this work concerns the sealing of the terraces, an operation carried out as part of the Plan for the Recovery of the Economy, and on the Church of Our Lady of Galilee, the repair of electrical installations and the installation of lighting for enhancement.
The Cathedral of Saint-Dié-des-Vosges
Repairing the waterproofing of the terraces
The Cathedral of Saint-Dié-des-Vosges, property of the State - Ministry of Culture, classified as a historical monument since 1886, constitutes, with the Church of Our Lady of Galilee and the cloister that connects them, a cathedral ensemble having known successive contributions, reconstructions and reshapings and different styles, unified by the pink sandstone color of the Vosges.
Construction began at the end of December 2021. The concrete terraces have been replaced by new roofs, with copper cladding and tile roofs on the north and south sides restored.
At the same time, the restoration of the walls of the interior vaults located on the terraces is also carried out.
The intervention, amounting to 434,742 euros, is carried out as part of the economic recovery plan (100% state).
Our Lady of Galilee Church
Electrical installations and development lighting
Work is also being done for the Church of Our Lady of Galilee. This building, also listed in 1886, is a remarkable example of South Lorraine Romanesque art. Having escaped destruction during the Second World War, the building retains the provisions dating from its reconstruction in XIIe century, after the fire of 1155.
The work is aimed at renewing the electrical installations and lighting highlighting the interior of the church. The quality of the lighting will be improved thanks to a suitable number of projectors, installed at the level of the cornice and the shafts of the column capitals.
In order to harmonize the integration of these installations, accompanying works have also been planned to pave the soil. These were carried out under the control of the DRAC Grand Est - Service régional de l'archéologie.
The recovery in search of plaster and the general repair of the brush on the vaults and the walls of the tribune must complete this intervention.
This operation is also financed entirely by the State - DRAC Grand Est, for an amount of 644,257 euros.
Saint-Dié-des-Vosges Cathedral
Amount of work EUR 434,742, financed by the State, under the Economic Recovery Plan
Réfection sealing the low terraces of the North and South towers
Construction time : estimated at 7 months, start of work end 2022
Contracting authority : Regional Directorate for Cultural Affairs of the Great East
Project management : Riccardo GIORDANO - Arch-R, Chief Architect of Historical Monuments
Companies
Lot 01: construction plant, scaffolding and protection, masonry, face stone
PIANTANIDA SAS
8, rue de Moulins sur Allier 88580 - SAULCY SUR MEURTHE
Lot 02: Frame, carpentry
MADDALON FRERES SARL
ZA Le Foulon 54121 - VANDIERE
Lot 03: Cover
MADDALON FRERES SARL
ZA Le Foulon 54121 - VANDIERE
Church of Our Lady of Galilee
Electrical Retrofit and Enhancement Lighting
Amount of work State-funded: 644,257 euro - Regional Directorate for Cultural Affairs
Construction time Estimated to be 9 months, start of work in January 2022
Contracting authority : Regional Directorate for Cultural Affairs of the Great East
Project management : Riccardo GIORDANO - Arch-R, Chief Architect of Historical Monuments
Companies
Lot 01: Masonry, cut stone
PIANTANIDA SAS
8, rue de Moulins sur Allier 88580 - SAULCY SUR MEURTHE
Lot 02: Electricity
SAS SODEL
8 rue du 12e Artillery BP 22 - 88101 - SAINT-DIE Cedex
Lot 03: Archaeological excavations
National Institute for Preventive Archaeological Research
12, rue de Méric 57063 - METZ